Tata Power Closes 135MW Amakhala Wind Project

India’s Tata Power has announced the financial closure for its 134MW Amakhala Emoyeni wind farm project through its South African joint venture company with Exxaro – Cennergi.

The company was selected as the preferred bidder for the Amakhala wind farm project and the 95MW Tsitsikamma wind farm project by the South African government’s department of energy in 2012.

Cennergi has successfully tied up the entire debt requirement through a consortium of lenders, namely Standard Bank and International Finance Corporation, with Standard Bank acting as the mandated lead arranger. The signing of financing agreements was completed on May 9, 2013. The company also completed pre-disbursement conditions under the financing agreements for availing interim disbursement and received the first loan disbursement on June 3, 2013.

The project of approximately R3,945mn is being funded through a debt equity mix of 80:20. The project financing comprises equity of R789mn and term loans of R3,156mn.

The company’s other 95MW Tsitsikamma community wind farm is also expected to achieve financial closure in a week. The wind projects will be located in Eastern Cape, South Africa, and are expected to achieve commercial operations in 2016. Power purchase agreements and implementation agreements for these projects were signed with Eskom and the department of energy on May 9, 2013.

Cennergi is 50:50 joint venture between South Africa’s Exxaro Resources and Tata Power.

“The signing of financing agreements is a significant milestone for the project,” said Anil Sardana, chairman, Cennergi, and managing director, Tata Power. Cennergi, based in South Africa, focuses on the investigation of feasibility, development, ownership, operation, maintenance, acquisition and management of electricity generation projects in South Africa, Botswana and Namibia. The initial project pipeline focuses on renewable energy projects in Southern Africa and Cennergi’s strategy is to create a balanced portfolio of generation assets.

 

Pimagazine Asia Admin

Recent Posts

Insuring Wind Turbines, What is the Risk?

Gallagher Re has shed light on the significant challenges insurers face when providing coverage for…

2 months ago

ARENA Start Feasibility Study in Western Australia

The Australian government will disburse AUD 1.7 million (USD 1.1m/EUR 1m) in grant funding to…

2 months ago

Asia moving away from Solar?

GlobalData’s latest report, ‘Asia Pacific Renewable Energy Policy Handbook 2024’ is among the latest region-specific…

2 months ago

Asia’s Energy Challenge 2024

The electrical generation market is facing a number of challenges, including the need to increase…

2 months ago

Powering Progress: Nuclear Energy’s Role in Asia’s Energy Landscape

Nuclear energy has emerged as a prominent player in Asia's energy landscape, offering a reliable…

7 months ago

Charting a Cleaner Path: Carbon Capture and Storage in Asia

The pursuit of a low-carbon future has gained significant momentum globally, and Asia stands tall…

7 months ago