Categories: NewsPower Generation

Is competitive bidding a successful business model for the Malaysian power industry?

Independent power producers (IPPs) believe problems with acquiring a suitable new site and the wayleave for the transmission line for the proposed 2,000MW (2×1,000MW) coal-fired power plant tender will limit participation to companies with deep pockets and Tenaga Nasional Bhd (TNB).

“It’s going be quite difficult to find the right location for the project site and even more challenging to get landowners to sell land for the transmission line — they are going to ask for inflated prices and IPPs don’t have the power to forcefully acquire the land,” said a spokesperson with a local IPP.

The greenfield plant tendered under so-termed package 3B has been called by the Energy Commission (EC). The request for qualification (RFQ) requires for the construction of the transmission lines from the proposed site to the nearest nodal point including procurement of all necessary wayleave.

As it stands, the fast-track brownfield 1,000MW Package 3A coal-fired power plant open tender that required interconnection facility and wayleave, attracted two bidders in TNB and 1Malaysia Development Bhd (1MDB) with their respective foreign partners despite 30 companies having RFQ for both the packages.

Under relevant acts, TNB is solely responsible for the construction of all transmission line connectivity from a power plant to the nearest nodal point and to procure all necessary wayleave associated with it, the spokesperson added. The RFQ conditions for Package 3A and 3B, IPPs say, would give TNB a significant advantage in the bidding process.

The RFQ conditions and 1MDB’s proposed purchase of the 1,400MW coal-fired power plant in Jimah, Negri Sembilan, from Jimah EnergyVentures Sdn Bhd’s two shareholders, minus the 20% held by TNB in the IPP, suggest that the federal government want more control of the power generation sector.

Some believe 1MDB’s generous offer of a reported RM1.7 billion for the Jimah stake could encourage other IPP owners to cash out as well in the days to come. Other IPPs were reported to be offering at best RM1 billion for Jimah earlier.

1MDB has already spent RM10.8 billion last year to acquire the generation assets of the Genting Group and Tanjung Energy Holdings Sdn Bhd from billionaire Tan Sri T Ananda Krishnan.

The offer comes as 1MDB has proposed to build the new 1,000MW Package A facility at Jimah’s site near Bukit Pelanduk in Negri Sembilan.

The deal, if concluded, will take its total generation capacity to about 3,600MW in anticipation of a possible listing of the group on the local stock exchange later this year.

Pimagazine Asia Admin

Recent Posts

Insuring Wind Turbines, What is the Risk?

Gallagher Re has shed light on the significant challenges insurers face when providing coverage for…

1 month ago

ARENA Start Feasibility Study in Western Australia

The Australian government will disburse AUD 1.7 million (USD 1.1m/EUR 1m) in grant funding to…

1 month ago

Asia moving away from Solar?

GlobalData’s latest report, ‘Asia Pacific Renewable Energy Policy Handbook 2024’ is among the latest region-specific…

1 month ago

Asia’s Energy Challenge 2024

The electrical generation market is facing a number of challenges, including the need to increase…

1 month ago

Powering Progress: Nuclear Energy’s Role in Asia’s Energy Landscape

Nuclear energy has emerged as a prominent player in Asia's energy landscape, offering a reliable…

7 months ago

Charting a Cleaner Path: Carbon Capture and Storage in Asia

The pursuit of a low-carbon future has gained significant momentum globally, and Asia stands tall…

7 months ago