India-Bangladesh transmission network to face significant delays

Delays on either side of the Indo-Bangla border in laying transmission facilities have cast a shadow on the timely launch of power trade between the two countries.

India is scheduled to supply up to 500 MW of electricity, through long-term agreements, to the neighbouring country via the international border at Baharampur in Murshidabad district of West Bengal.

Of the total, 250 MW will be supplied by state-owned NTPC Ltd at a regulated tariff.

Bangladesh may procure an additional 250 MW from the open market.

A crucial milestone of the bilateral agreement entered in Delhi in January 2010, the project was originally scheduled to be operational in 2012. As per the revised timeline, Power Grid Corporation of India Ltd (PGCIL) and Power Grid Company Bangladesh (PGCB) are expected to complete the respective portions of the project work in May 2013 and July 2013, respectively.

DELAY BY PGCIL

However, information available suggests that local disputes in erecting two transmission towers, out of 197, may force PGCIL to miss the May 2013 deadline.

Slated to lay a 71-km high-voltage (400 KV, double-circuit) transmission network from Baharampur to Bheramara in Bangladesh, Power Grid has so far been able to complete only a 50-km stretch.

The company has, however, completed the rest of the project work, including a switching substation at Baharampur and a peripheral 2.5-km network.

The total project cost on the Indian side is estimated at Rs 160 crore.

Meanwhile, Bangladesh has also registered equally slow progress in implementing the Rs 737-crore ($156 million) transmission facilities.

The project is part-financed by the Asian Development Bank.

Sources suggest that the construction of a 500 MW substation (high-voltage, double-circuit, back-to-back station) at Bheramara may not be completed by the July 2013 deadline.

The project has been particularly impacted by the recent spate of bandhs in Bangladesh, affecting movement of imported equipment from the ports to Bheramara.

Of the 31-km transmission line to be constructed, PGCB has so far completed 27 km. The rest of the project is expected to be finished this month.

Pimagazine Asia Admin

Recent Posts

Insuring Wind Turbines, What is the Risk?

Gallagher Re has shed light on the significant challenges insurers face when providing coverage for…

2 months ago

ARENA Start Feasibility Study in Western Australia

The Australian government will disburse AUD 1.7 million (USD 1.1m/EUR 1m) in grant funding to…

2 months ago

Asia moving away from Solar?

GlobalData’s latest report, ‘Asia Pacific Renewable Energy Policy Handbook 2024’ is among the latest region-specific…

2 months ago

Asia’s Energy Challenge 2024

The electrical generation market is facing a number of challenges, including the need to increase…

2 months ago

Powering Progress: Nuclear Energy’s Role in Asia’s Energy Landscape

Nuclear energy has emerged as a prominent player in Asia's energy landscape, offering a reliable…

7 months ago

Charting a Cleaner Path: Carbon Capture and Storage in Asia

The pursuit of a low-carbon future has gained significant momentum globally, and Asia stands tall…

8 months ago